-->

Type something and hit enter

Pages

Singapore Investment


On


Jaks Resources – The Final Count Down ! (update)
Hai Duong coal power plant. Photo taken on 27 January 2020
 
 
Progress
CPECC officially announced that the construction of the power plant has entered testing phase effective 1st October 2019.
All 4 Boilers have successfully carried out hydro tests 
Both turbines have completed installation of turbine rotors. 
1st coal arrived
Boilers 1 & 2 have completed Chemical cleaning.
Boiler 1 has successfully completed steam blow test on 20th Jan 2020
Boiler 2 should have completed steam blow test (waiting for confirmation)
 
The Unit 1 of the power plant is on schedule to commence commercial operation in Mid 2020 which is about 6 months ahead of deadline.
 
You may visit the link below for more latest photos of the construction progress. (Click on "latest")
 
DK66
P/S:  You may visit my blog for more articles on Jaks Resources.


https://klse.i3investor.com/blogs/Jaks%20resources/2020-01-31-story-h1482988876-Jaks_Resources_The_Final_Count_Down_Update.jsp

Back to Top