-->

Type something and hit enter

Pages

Singapore Investment


On

 LRT3继续跑,GKENT几时飞?

这个星期内,除了顶级手套的收购欺诈案的劲爆新闻以外,另一个我比较关注的新闻就是关于轻快铁LRT3工程的命运了。

从第14届大选结束后,很多大型基建工程(如:隆新高铁、MRT3)都纷纷被搁置。这一系列的政府撙节措施,令到多间上市建筑公司的股票大幅下调。其中一间是GKENT。基于当时我觉得该公司手上的合约(即LRT3)并没有被影响,也应该不会被终止(因为工程已经在进行中了),所以我也趁机在股价大跌时(我认为被低估了)买入了一点。

殊不知,昨天财政部长检讨了LRT3的总成本暴涨许多,因此指示国家基建公司(Prasarana)必须大幅削减。此举令到市场担心工程会被停工,作为工程执行伙伴(PDP)的GKENT马上应声下跌。

才过了一天,今天内阁同意削减工程成本(47%)的提案,正式宣布让LRT3继续建造。这项决定终于扫除了这个工程的不确定性,与我心头最大的忧虑。这个消息确定后,我对之前的投资判断也更有信心,所以还会继续持有GKENT股票。目前为止,我在这项GKENT的投资仍然处于纸上亏损的。

详细的工程成本削减方案可以拜读以下The Star的新闻报导:



Source from The Star Online


KUALA LUMPUR: The Cabinet has given the go-ahead for the continuation of the 37-km long light rail transit  (LRT) 3 project  but the final cost  has been reduced by 47% to RM16.63bil.

Finance Minister Lim Guan Eng said on Thursday the Cabinet gave its approval during the meeting on Wednesday and the final cost will enable Malaysians to save a total of RM15.02bil.

The completion date for the LRT 3, stretching from Johan Setia (Klang) to Bandar Utama (Petaling Jaya), was extended from 2020 to 2024 to further reduce construction cost which was inflated.

The construction of the LRT3 project will be restructured from a project-delivery-partner (PDP) model to a “fixed price contract” with the joint venture of MRCB and George Kent, he said.

“This will ensure that the price will be fixed and will not be subject to cost overruns. The details of this contract will be disclosed at a later stage,” he added.

The savings of more than RM15bil would not only mean a massive reduction of RM15bil in debt to be incurred, but also result in additional savings to the tax-payers of up to RM14bil in interest cost over the period of the loan financing.

“The 47% reduction in cost demonstrates that the new Federal Government is walking the talk in securing significant cost reductions for excessively-priced project caused by the poor governance of the previous government,” said Lim.

“This cost will include all project costs, including but not limited to work package contracts (WPC), land acquisition, project management, consultancy fees, operational and overhead costs, as well as interest during construction,” he said.

To recap, on March 30, 2018, Prasarana submitted the latest projected cost of the LRT3 project which amounted to RM31.65bil.

At the same time, Prasarana sought an additional financing of RM22bil in the form of government guarantees, on top of the initial RM10bil granted in 2015 to finance the project.

Lim said the LRT3 project is a critical project meant to alleviate the issue of traffic congestion along one of the most important and densely populated economic development corridors in the Klang Valley, from Klang to Petaling Jaya.

The new LRT line is expected to serve a two-million population with the capacity to transport 36,700 passenger per hour each way.

A thorough renegotiation and rationalization exercise of the LRT3 project was undertaken with all key stakeholders including Prasarana, MRCB-GK JV and the Land Public Transportation Commission (SPAD).

One critical criteria for the review was that the integrity of the 37km LRT3 line must be maintained. In addition, the safety, frequency and quality of service must meet the requirements of the regulators.

Key steps taken to reduce and rationalise project costs include:

(i) Reducing the order of 42 sets of six-car trains to 22 sets of three-car trains. Based on the feasibility study of the LRT3 project, the 22 sets of three-car trains is more than sufficient
to cope with the anticipated passenger demand until the year 2035 before additional three-car trains need to be ordered.

(ii) Reducing the construction size of the LRT train depot due to the significantly reduced number of LRT trains to be acquired.

(iii) Streamlining the size and design of the LRT stations based on Kelana Jaya LRT line standards instead of being benchmarked against the much larger MRT stations.

(iv) Shelving the construction of 5 stations with very low projected passenger ridership until such a time the demand is deemed necessary for these stations to be built. These
provisional stations are Lien Hoe, Temasya, SIRIM, Bukit Raja and Bandar Botanic.

(v) Cancelling an unnecessary 2km tunnel for the LRT together with an underground station at Persiaran Hishamuddin, Shah Alam.

(vi) Extending the timeline to complete the LRT3 project from 2020 to 2024 in order to further reduce construction cost which was inflated due to "acceleration costs" i.e. to
speed up the project incurs additional costs.

Read more at https://www.thestar.com.my/business/business-news/2018/07/12/final-price-of-lrt3-reduced-by-47pct-to-rm16pt63b-says-prasarana/

https://greedbminvest.blogspot.com/2018/07/lrt3gkent.html
Back to Top