TALIWRK (8524) TALIWORKS CORP BHD wins RM602m contract to develop package for Sungai Rasau water plant
KUALA LUMPUR (Dec 16): Taliworks Corp Bhd has won a contract from Pengurusan Air Selangor Sdn Bhd to develop a package under Phase 1 of the Sungai Rasau water treatment plant for RM602.43 million.
The contract is to design and build a water pumping station, and water pumping mains to the existing Bukit Lipat Kajang reservoirs, distribution and associated works (Package 2), the company said in a bourse filing.
“The date of the site possession shall be on Dec 29, 2021. The completion date for the works shall be on Dec 31, 2024 i.e. 36 months from the date of the possession of the site,” Taliworks said.
The Edge reported in October that as many as nine bidders submitted their bids for the construction of the 700 million litres-a-day water treatment plant, where the tender — valued at between RM1.7 billion and RM2 billion — was called back in May.
It is understood that other listed companies which bid for the project included IJM Corp Bhd, Gamuda Bhd, and Salcon Bhd, according to the report.
Shares of Taliworks settled unchanged at 85.5 sen, giving the company a market capitalisation of RM1.72 billion.
http://www.theedgemarkets.com/article/taliworks-wins-rm602m-contract-develop-package-sungai-rasau-water-plant
Singapore Investment
-
-
US Supreme Court upholds TikTok ban4 hours ago
-
-
-
S$500: Big Sign-up Offer For StanChart Cards!11 hours ago
-
-
-
Life is short14 hours ago
-
-
OCBC Bank – Delivering, but need clarity20 hours ago
-
-
-
-
New Home Defects Talk1 day ago
-
-
-
-
-
-
7 Ways to Tackle Credit Card Debt2 days ago
-
Finance Investment Movement 532 days ago
-
-
-
-
-
-
-
-
#ReturnOurCPF $$4 days ago
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
My New Year CPF routine1 week ago
-
-
-
-
-
-
-
-
-
A Review of 20242 weeks ago
-
-
-
-
-
-
Dec 2024 Portfolio2 weeks ago
-
-
4Q 2024 Investment Strategy Update2 weeks ago
-
Portfolio (Dec 31, 2024)2 weeks ago
-
Top 10 Highlights of 20242 weeks ago
-
-
Portfolio Summary for December 20242 weeks ago
-
-
-
-
-
UOB Home Loan3 weeks ago
-
Why do I question about life?3 weeks ago
-
-
-
Quick Update, Some Links/News3 weeks ago
-
-
-
-
Random thoughts: Sickness...5 weeks ago
-
-
-
A contrarian’s wet dream?1 month ago
-
Reflections for year 20241 month ago
-
-
My Palantir Regret1 month ago
-
-
-
-
-
-
-
Union Square Residences2 months ago
-
-
-
-
-
Tax Relief for Topping Up Spouse CPF: Guide3 months ago
-
-
China boom?3 months ago
-
-
STI ETF3 months ago
-
-
-
-
Unibet Casino Bonus Codes 20244 months ago
-
-
-
MSC: Mission Critical distributor4 months ago
-
500k Milestone!5 months ago
-
-
-
-
-
-
-
-
Monthly IBKR Update – June 20246 months ago
-
-
-
-
-
-
-
Breakthroughs in portfolio :)7 months ago
-
-
-
Feb 2024 Expenditure9 months ago
-
-
APAC Markets: First Trends in 202410 months ago
-
-
-
-
-
Monthly Summary of November 20231 year ago
-
Migration of website1 year ago
-
-
-
-
-
-
-
-
-
-
A New Light1 year ago
-
-
-
-
-
-
2022 Thoughts, Hello 2023!2 years ago
-
Series of Defaults for Maple Finance2 years ago
-
Takeaways from “Sea Change”2 years ago
-
Greed is Coming Back2 years ago
-
-
Investing is Easy2 years ago
-
-
-
-
-
-
-
-
What is Overemployment2 years ago
-
Terra Hill Condo (former Flynn Park)2 years ago
-
Alibaba VS Tencent: The Battle Royale2 years ago
-
-
-
-
-
-
-
-
-
-
-
-
Home
TALIWRK
TALIWRK (8524) TALIWORKS CORP BHD wins RM602m contract to develop package for Sungai Rasau water plant